Ace With Ease IAS Academy Ace With Ease
UPSC Prelims PYQ
Practise online

UPSC Prelims PYQ › Quantitative Aptitude › Time & Work, Pipes

Time & Work, Pipes — UPSC CSAT Paper II Quantitative Aptitude previous year questions

20 free solved previous year questions on Time & Work, Pipes, papers from 2013 to 2025, drawn from UPSC CSAT, UPSC CDS, covering questions of the kind UPSC asks in CSAT Paper II. Every answer key has been checked again against published sources and solved independently, and each explanation is written fresh.

20 free questions
117 more with full access
Quantitative Aptitude
Start 20 free questions →
Read all 20 questions with answers
  1. #1UPSC CSAT 2025
    A set (X) of 20 pipes can fill 70% of a tank in 14 minutes. Another set (Y) of 10 pipes fills 3/8th of the tank in 6 minutes. A third set (Z) of 16 pipes can empty half of the tank in 20 minutes. If half of the pipes of set X are closed and only half of the pipes of set Y are open, and all pipes of the set (Z) are open, then how long will it take to fill 50% of the tank?
    • A8 minutes
    • B10 minutes
    • C12 minutes
    • D16 minutes
    Answer: (D) 16 minutes
    Explanation

    Rates per minute (as % of tank): 10 pipes of X give 2.5, 5 pipes of Y give 3.125, and Z drains 2.5.
    Net filling rate = 2.5 + 3.125 - 2.5 = 3.125% per minute.
    Time for 50% = 50/3.125 = 16 minutes.
    Answer: option (d).

    Source: UPSC CSAT 2025 question; answer key checked by independent computation

  2. #2UPSC CSAT 2025
    X can complete one-third of a certain work in 6 days, Y can complete one-third of the same work in 8 days and Z can complete three-fourth of the same work in 12 days. All of them work together for n days and then X and Z quit and Y alone finishes the remaining work in 8 2/3 days. What is n equal to?
    • A3
    • B4
    • C5
    • D6
    Answer: (B) 4
    Explanation

    Full-work times: X 18 days, Y 24 days, Z 16 days. Combined rate = 1/18 + 1/24 + 1/16 = 23/144 per day.
    Y alone does (26/3)/24 = 13/36 of the work at the end, so the team did 23/36 earlier.
    n = (23/36) / (23/144) = 4.
    Answer: option (b).

    Source: UPSC CSAT 2025 question; answer key checked by independent computation

  3. #3UPSC CSAT 2024
    A certain number of men can complete a piece of work in 6k days, where k is a natural number. By what percent should the number of men be increased so that the work can be completed in 5k days?
    • A10%
    • B(50/3)%
    • C20%
    • D25%
    Answer: (C) 20%
    Explanation

    Men and days are inversely proportional: N1 x 6k = N2 x 5k, so N2 = 1.2 N1.
    The increase is 20%.
    Answer: option (c).

    Source: UPSC CSAT 2024 question; answer key checked by independent computation

  4. #4UPSC CSAT 2024
    X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. However, only one person at a time can work in each hour and nobody can work for two consecutive hours. All are engaged to finish the work. What is the minimum amount of time that they will take to finish the work?
    • A6 hours 15 minutes
    • B6 hours 30 minutes
    • C6 hours 45 minutes
    • D7 hours
    Answer: (C) 6 hours 45 minutes
    Explanation

    Take the work as 24 units: X does 4 per hour, Y and Z do 3 each.
    Best plan is X in odd hours and Y/Z alternately in even hours: after 6 hours 3 x 4 + 3 x 3 = 21 units; 6 hours cannot reach 24.
    The last 3 units go to X at 4 per hour, i.e. 45 minutes, total 6 h 45 min.
    Answer: option (c).

    Source: UPSC CSAT 2024 question; answer key checked by independent computation

  5. #5UPSC CSAT 2023
    A, B, C working independently can do a piece of work in 8, 16 and 12 days respectively. A alone works on Monday, B alone works on Tuesday, C alone works on Wednesday; A alone, again works on Thursday and so on. Consider the following statements:1. The work will be finished on Thursday.2. The work will be finished in 10 days.Which of the above statements is/are correct?
    • A1 only
    • B2 only
    • CBoth 1 and 2
    • DNeither 1 nor 2
    Answer: (A) 1 only
    Explanation

    Take total work 48 units: A does 6, B does 3, C does 4 per day.
    Every 3 days give 13 units, so 9 days give 39 units; day 9 is a Tuesday if day 1 is Monday.
    Day 10 (Wednesday, A) adds 6 to make 45; day 11 (Thursday, B) adds the last 3.
    So the work ends on Thursday, in 11 days: statement 1 true, statement 2 false.
    Answer: option (a).

    Source: UPSC CSAT 2023 question; answer key checked by independent computation

  6. #6UPSC CSAT 2022
    24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
    • A30 days
    • BMore than 30 days
    • CLess than 30 days or more than 30 days
    • DData is inadequate to draw any conclusion
    Answer: (D) Data is inadequate to draw any conclusion
    Explanation

    Let a man's rate be m and a woman's rate be w, so 24m + 12w = 1/30.
    The second group has rate 12m + 24w. This equals the first only if m = w; otherwise it is larger or smaller.
    Since the relative efficiency is unknown, nothing definite can be said.
    Answer: option (d).

    Source: UPSC CSAT 2022 question; answer key checked by independent computation

  7. #7UPSC CSAT 2021
    A man completes 7/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50%?
    • A24
    • B21
    • C18
    • D15
    Answer: (D) 15
    Explanation

    Full job takes 21 x 8/7 = 24 days.
    With 50% more work, total time = 24 x 1.5 = 36 days.
    Already worked 21 days, so 36 - 21 = 15 more days.
    Answer: option (d).

    Source: UPSC CSAT 2021 question; answer key checked by independent computation

  8. #8UPSC CSAT 2020
    A person X can complete 20% of work in 8 days and another person Y can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?
    • A6
    • B8
    • C10
    • D12
    Answer: (A) 6
    Explanation

    X's rate = 1/40 per day (full work in 40 days); Y's rate = 1/24 per day.
    Together = 1/40 + 1/24 = 1/15 per day, i.e. the whole job in 15 days.
    40% of the work takes 0.4 x 15 = 6 days.
    Answer: option (a).

    Source: UPSC CSAT 2020 question; answer key checked by independent computation

  9. #9UPSC CSAT 2016
    Ram and Shyam work on a job together for four days and complete 60% of it. Ram takes leave then and Shyam works for eight more days to complete the job. How long would Ram take to complete the entire job alone?
    • A6 days
    • B8 days
    • C10 days
    • D11 days
    Answer: (C) 10 days
    Explanation

    Shyam does the remaining 40% in 8 days, i.e. 5% per day.
    Together they do 60%/4 = 15% per day, so Ram does 10% per day.
    Ram alone needs 100/10 = 10 days.
    Answer: option (c).

    Source: UPSC CSAT 2016 question; answer key checked by independent computation

  10. #10UPSC CSAT 2016
    W can do 25% of a work in 30 days, X can do 1/4 of the work in 10 days, Y can do 40% of the work in 40 days and Z can do 1/3 of the work in 13 days. Who will complete the work first?
    • AW
    • BX
    • CY
    • DZ
    Answer: (D) Z
    Explanation

    Full-work times: W = 120 days, X = 40 days, Y = 100 days, Z = 39 days.
    Z needs the fewest days.
    Answer: option (d).

    Source: UPSC CSAT 2016 question; answer key checked by independent computation

  11. #11UPSC CSAT 2015
    Two pipes A and B can independently fill a tank completely in 20 and 30 minutes respectively. If both the pipes are opened simultaneously, how much time will they take to fill the tank completely?
    • A10 minutes
    • B12 minutes
    • C15 minutes
    • D25 minutes
    Answer: (B) 12 minutes
    Explanation

    Combined rate = 1/20 + 1/30 = 5/60 = 1/12 tank per minute.
    Time = 12 minutes.
    Answer: option (b).

    Source: UPSC CSAT 2015 question; answer key checked by independent computation

  12. #12UPSC CSAT 2013
    In a garrison, there was food for 1000 soldiers for one month. After 10 days, 1000 more soldiers joined the garrison. How long would the soldiers be able to carry on with the remaining food?
    • A25 days
    • B20 days
    • C15 days
    • D10 days
    Answer: (D) 10 days
    Explanation

    Food is 1000 x 30 = 30,000 soldier-days (taking a month as 30 days). In 10 days 10,000 are used, leaving 20,000.
    With 2000 soldiers, 20,000/2000 = 10 days.
    Answer: option (d).

    Source: UPSC CSAT 2013 question; answer key checked by independent computation

  13. #13UPSC CDS 2023
    If A and B finish a work in 10 days, B and C can finish the same work in 12 days, C and A can finish the same work in 15 days; then in how many days can A, B and C together finish half of the work?
    • A8 days
    • B5 days
    • C4 days
    • D3 days
    Answer: (C) 4 days
    Explanation

    Take total work as 60 units. A+B = 6, B+C = 5, C+A = 4 units per day.
    Adding, 2(A+B+C) = 15, so A+B+C = 7.5 units per day.
    Half the work = 30 units, so time = 30/7.5 = 4 days.
    Answer: option (c).

    Source: UPSC CDS 2023 question; answer key checked by independent computation

  14. #14UPSC CDS 2023
    Three persons A, B and C together can do a piece of work in 36 days. A and B together can do five times as much work as C alone; B and C together can do as much work as A alone. If A and C together can do n times as much work as B alone, then what is the value of n?
    • A1.5
    • B2
    • C2.5
    • D3
    Answer: (B) 2
    Explanation

    Rates: A+B+C = 1/36, A+B = 5C gives 6C = 1/36, so C = 1/216.
    B+C = A gives 2A = 1/36, so A = 1/72, and B = 1/72 - 1/216 = 1/108.
    A + C = 1/54, which is 2 times B (1/108).
    Answer: option (b).

    Source: UPSC CDS 2023 question; answer key checked by independent computation

  15. #15UPSC CDS 2023
    A can do a certain work at twice the speed of B. Further, B can do the same work at 1.5 times the speed of C. All of them together can finish the work in 12 days. In how many days can C alone finish the work?
    • A36 days
    • B45 days
    • C60 days
    • D66 days
    Answer: (D) 66 days
    Explanation

    Let C's speed be 1 unit; then B = 1.5 and A = 3, total 5.5 units per day.
    Work = 5.5 x 12 = 66 units.
    C alone takes 66/1 = 66 days.
    Answer: option (d).

    Source: UPSC CDS 2023 question; answer key checked by independent computation

  16. #16UPSC CDS 2023
    If 17 women and 24 men can do a piece of work in 5 days and 12 women and 23 men can do it in 6 days, then which one of the following is correct?
    • AEfficiency of 13 women = Efficiency of 18 men
    • BEfficiency of 11 women = Efficiency of 16 men
    • CEfficiency of 13 women = Efficiency of 17 men
    • DEfficiency of 11 women = Efficiency of 15 men
    Answer: (A) Efficiency of 13 women = Efficiency of 18 men
    Explanation

    Total work is the same: 5(17W + 24M) = 6(12W + 23M).
    85W + 120M = 72W + 138M, which gives 13W = 18M.
    Answer: option (a).

    Source: UPSC CDS 2023 question; answer key checked by independent computation

  17. #17UPSC CDS 2023
    Three taps A, B and C together can fill a tank in 6 hours. Tap C alone can fill the tank in 12 hours. To fill the tank, when it is empty, all the three taps are started together. After working t hours, tap C is closed and the tank is filled in 8 more hours. What is t equal to?
    • A1
    • B2
    • C4
    • D6
    Answer: (B) 2
    Explanation

    A + B together fill 1/6 - 1/12 = 1/12 of the tank per hour.
    In the last 8 hours they fill 8/12 = 2/3 of the tank.
    So the first t hours must fill 1/3: t/6 = 1/3, hence t = 2.
    Answer: option (b).

    Source: UPSC CDS 2023 question; answer key checked by independent computation

  18. #18UPSC CDS 2023
    A, B and C can complete a work in x, 1.5x and 2x days respectively. If they complete the work together, in what ratio should they be paid?
    • A2:3:4
    • B6:4:3
    • C3:2:1
    • D4:3:2
    Answer: (B) 6:4:3
    Explanation

    Payment is in the ratio of work done, i.e. of daily rates when all work for the same time.
    Rates are 1/x : 1/(1.5x) : 1/(2x) = 1 : 2/3 : 1/2.
    Multiplying by 6 gives 6 : 4 : 3.
    Answer: option (b).

    Source: UPSC CDS 2023 question; answer key checked by independent computation

  19. #19UPSC CDS 2022
    X and Y can do a piece of work in 45 days and 40 days respectively. They begin to work together, but X leaves after n days and then Y completes the remaining work in 23 days. What is n equal to?
    • A8
    • B9
    • C10
    • D12
    Answer: (B) 9
    Explanation

    Together they do 1/45 + 1/40 = 17/360 per day.
    Y alone does 23/40 in 23 days, so the joint work is 1 - 23/40 = 17/40.
    n x 17/360 = 17/40 gives n = 9.
    Answer: option (b).

    Source: UPSC CDS 2022 question; answer key checked by independent computation

  20. #20UPSC CDS 2022
    480 persons working 10 hours per day complete one-fourth of a work in 10 days. How many additional persons are to be employed in order to complete the remaining work in 20 days, working 8 hours per day?
    • A400
    • B420
    • C480
    • D500
    Answer: (B) 420
    Explanation

    One-fourth of the work = 480 x 10 x 10 = 48,000 man-hours, so the remaining three-fourths = 144,000 man-hours.
    Persons needed = 144000/(20 x 8) = 900.
    Additional persons = 900 - 480 = 420.
    Answer: option (b).

    Source: UPSC CDS 2022 question; answer key checked by independent computation

Want all the Time & Work, Pipes questions?

117 more questions on this topic, plus mock tests, revision and progress tracking, are in the full practice set. One payment of ₹499.

Get full access – ₹499 Already have a code? Unlock here

More Quantitative Aptitude topics

Data Sufficiency20 free questionsAlgebra & Equations20 free questionsPermutation, Combination & Probability20 free questionsNumber System & Basic Numeracy20 free questionsTime, Speed & Distance20 free questionsGeometry & Mensuration20 free questionsAverage, Mixtures & Alligation20 free questionsRatio, Proportion & Partnership20 free questionsPercentage, Profit & Loss20 free questionsSeries, Clocks, Calendar & Miscellaneous20 free questionsData Interpretation20 free questionsSimple & Compound Interest20 free questions
Preparing for UPSC? Sit in a live class first. Free counselling + live GS demo class with Shiva Teja Sir, Hyderabad or online.
Book a free demo class